two trains of metro line 1 in thu duc city Two trains of Metro Line 1 in Thu Duc city

12:59 | 15/05/2021

The second and third train carriages of Metro Line 1 were imported successfully so that operations can begin on schedule.

floor b1 of ba son underground station of metro line 1 completed Floor B1 of Ba Son underground station of Metro Line 1 completed

18:26 | 06/05/2021

Floor B1 of Ba Son Station of Metro Line 1 (Ben Thanh-Suoi Tien) has basically been completed 31 days earlier than planned.

metro line no1 on the home straight Metro Line No.1 on the home straight

16:13 | 27/02/2019

VIR visited the construction site of Metro Line No.1, a symbol of Vietnamese-Japanese friendship, which is forecast to be completed in 2020.